@@ -2,10 +2,10 @@
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
current_phase: 2
current_plan: 02 - User Implementation (next)
status: executing
last_updated: "2026-03-24T21:33:00.753Z"
current_phase: 3
current_plan: Not started
status: planning
last_updated: "2026-03-24T21:35:41.930Z"
progress:
total_phases: 10
completed_phases: 2
@@ -16,7 +16,7 @@ progress:
# STATE: Laboratori Cloud - Corso Soluzioni Cloud
**Last Updated:** 2026-03-24
**Current Phase:** 2
**Current Phase:** 3
**Overall Progress:** 1/10 phases complete
---
@@ -37,7 +37,7 @@ Setup iniziale repository Git, configurazione ambiente di sviluppo, documentazio
## Current Position
**Phase:** 2 - Lab 01: IAM & Sicurezza
**Status:** Executing
**Status:** Ready to plan
**Plans:** 1/3 complete
**Progress Bar:**
@@ -46,7 +46,7 @@ Setup iniziale repository Git, configurazione ambiente di sviluppo, documentazio
Phase 2: [███░░░░░░] Plan 01 (Test Infrastructure) complete
```
**Current Plan:** 02 - User Implementation (next)
**Current Plan:** Not started
**What we're working on:**